Project

General

Profile

Feature #1478

Redmine : Assign the issues

Added by MASUDA Nao about 2 months ago. Updated about 1 month ago.

Status:
Resolved
Priority:
Urgent
Assignee:
Start date:
12/11/2025
Due date:
12/15/2025 (49 days late)
% Done:

100%

Estimated time:
2.00 h
Spent time:

Description

Putting in all the work done

#1

Updated by MASUDA Nao about 2 months ago

  • Status changed from New to In Progress
  • % Done changed from 10 to 20
#2

Updated by RAUT Yuvraj Anant about 2 months ago

  • Status changed from In Progress to Resolved
#3

Updated by MASUDA Nao about 2 months ago

  • % Done changed from 20 to 100
#4

Updated by MASUDA Nao about 1 month ago

  • Subject changed from Redmine to Redmine : Assign the issues
#5

Updated by MASUDA Nao about 1 month ago

  • Subject changed from Redmine : Assign the issues to Redmine : Assign the issues, Week11
#6

Updated by MASUDA Nao about 1 month ago

  • Subject changed from Redmine : Assign the issues, Week11 to Redmine : Assign the issues